Special Services Building Improvements


The improvements of the Special Services Building to house the Turner County Middle School began in January of 2014

February 5, 2016

The process began with the pressure washing of the exterior of the building.





February 8, 2016- Cleanup work begins to get the building ready for the improvements.











February 9, 2016








February 10, 2017







February 13, 2017









February 14, 2017






February 16, 2017






February 18, 2017





February 22nd, 2017


 February 23rd, 2017



 February 24th, 2017



 February 25th, 2017

 February 27th, 2017



February 27th, 2017 Floors being sanded


March 1st , 2017

March 2nd , 2017

March 3rd, 2017

March 4th, 2017

March 6th, 2017





March 7th, 2017



March 13th, 2017 - Door Replacement Begins





March 14th, 2017



March 15th, 2017


March 16th, 2017




March 17th, 2017


April 3rd, 2017






April 6th, 2017 Special Services Gym Improvements Begin






April 10th , 2017 Window Installation Begins

April 25th, 2017 Improvements continue




April 26th, 2017 Replacement of Water Fountain & Plumbing



April 27th, 2016 Awning work begins



May 11th Concrete Improvements Continue at Special Services Gym


Pressure Washing Begins at Special Services


May 11th Additional restroom improvements continue


May 11th Additional Wiring


May 11th Ceiling Tiles Replacement


May 12th, 2017



May 15th, 2017 Pressure Washing





May 16th, 2017


May 17th, 2017

Pressure Washing


Ceiling Tile Replacement

Windows Arrive





Additional Concrete

 May 18th, 2017 Getting ready for the move





May 18th, 2017 6th Grade Academy Improvements Start





 May 23rd, 2017 Playground equipment begins to be moved to elementary school


May 23th, 2017 Work Continues






May 24th, 2017 Fence Moving Begins

Painting Continues

Tile Work Moving Forward 



May 26th, 2017 The "Move" Goes Into Full Swing

Floor Waxing


Moving Pre-K 5-26-2017





June 1st, 2017



Playground Move Continues


June 4th, 6th Grade Academy Improvements Begin



June 8th, 2017 - Painting at the 6th grade academy gets underway



June 9th, 2017 - Commode Replacement at 6th Grade Academy

Before                                                                                     After


June 9th, 2017 - Playground move continues


June 10th, 2017 - Windows Installment Begins




June 13th, 2017

Light Fixtures changed out

Playground Continues to be moved


June 14, 2017 - Windows continue to be installed



June 15th, 2017 Work Continues



June 19th, 2017





June 19th, 2017 Continued

June 20th, 2017




June 22nd, 2017




June 27th, 2017




July 11th, 2017